Ask a room of commercial solar developers what kills projects late, and interconnection is named early and often. In California investor-owned utility territory — including Southern California Edison (SCE) — interconnection of generating and storage facilities is governed by Rule 21, the CPUC-jurisdictional tariff that sets application procedures, technical requirements, study paths and timelines. The CPUC's Rule 21 overview is the starting point: cpuc.ca.gov/rule21.
The five things that are not the same thing
Screening discipline starts with vocabulary. These are five different states, and no honest process skips steps between them:
| Stage | What it is |
|---|---|
| Public-data screen | A look at published hosting-capacity data and circuit information for the site's location. Triage only. |
| Interconnection application | A formal filing with the utility under Rule 21, with project technical data and fees. |
| Grid study | The utility's engineering review — fast-track screens first, detailed study where screens are not passed. |
| Interconnection agreement | The executed contract setting construction, upgrade scope, cost and schedule. |
| Permission to operate | Utility authorisation to energise, after construction, inspection and any required upgrades. |
What hosting-capacity data actually shows
SCE publishes Integration Capacity Analysis (ICA) results through its Distributed Energy Resources Interconnection Map (DERiM): the generation capacity a circuit can accommodate at a point, at the time of analysis, without thermal, voltage or protection violations. That is genuinely useful for triage — a site on a constrained circuit deserves early caution, and export vs non-export design choices can be weighed sooner. Two limits matter: ICA values change as queues and loads change, and Rule 21 fast-track screening compares a project against the applicable ICA values at its point of interconnection — passing a map check is not passing the screen, and passing the screen is not an agreement.
Export, non-export, and storage change the question
A behind-the-meter system sized to load, a non-export system with certified controls, a full-export generator and a battery that charges from the grid are four different interconnection conversations under the same tariff. Screening records which configuration a site implies — cold storage with high daytime load often supports a larger behind-the-meter system than its export capacity would suggest — and lists the formal steps that would follow.
The municipal-utility caveat
Rule 21 applies to the investor-owned utilities. Sites in LADWP, Anaheim, Riverside, Colton or Vernon public-power territory follow those utilities' own interconnection processes. POWWOD's grid screen starts by establishing which utility actually serves the parcel — using the California Energy Commission's service-territory data — before any Rule 21 framing is applied.
What POWWOD's grid screen delivers
Utility identification, configuration options, the published capacity picture with its source and date, upgrade-risk flags, the formal study path that would apply, and the information a developer's interconnection engineer will need next. It is a screen. Developers run their own studies, utilities make their own determinations, and POWWOD does not describe any site as interconnectable on screening evidence alone.
Background data source: California Distributed Generation Statistics publishes Rule 21 interconnection activity for the investor-owned utilities: californiadgstats.ca.gov.